Works are progressing well at site with the reinforced concrete frame already reaching the sixth floor on Core One and the roof of the penthouse on Core Two, the blockwork walls have commenced to the ground floor commercial office space and the apartment demise walls are starting to be laid out to the second floor.
· Core One Apartments – target completion is end April 2018.
· Core Two Apartments – target completion is mid- April 2018.